The Real Cost Behind a "Factory Price"

A founder sends us a quote: "$12.00 per unit, FOB." The question isn't whether $12 is fair — it's what is inside the $12, and what is not. Most first-time buyers budget off the unit price and get blindsided later by tooling, samples, testing, freight, and duty. This guide opens up the quote so you can see every line that exists — and every line that doesn't.

Why the quote isn't the price you pay

Three letters decide whether a quote means anything: EXW, FOB, CIF/DDP. They shift who pays for what — and if you don't know which one you were quoted, you don't have a price, you have a placeholder.

TermWhat the factory coversWhat you still pay
EXW
(Ex Works)
Making the goods. Pickup at their gate.Everything else: inland pickup, export clearance, freight, insurance, duty, delivery.
FOB
(Free On Board)
Goods + inland transport to the Chinese port + export clearance.Ocean/air freight, insurance, import duty, brokerage, final delivery.
CIF
(Cost, Insurance, Freight)
Goods + freight + insurance to your destination port.Import duty and taxes, customs brokerage, port charges, inland delivery.
DDP
(Delivered Duty Paid)
Everything to your door, duty included.Nothing on paper — but the landed cost is baked into a higher unit price, so you can't see the breakdown.

Two habits follow from this. First, always ask which Incoterm a price is quoted on before you compare anything. Second, build your own landed cost model rather than accepting DDP — because the moment you stop seeing the breakdown, you also stop seeing where the money can be saved.

1. Anatomy of a factory quote

A serious factory quote has roughly eight to ten lines. Most suppliers send one number. Asking for the breakdown is not aggressive — it is the single fastest way to look like a buyer they should treat seriously.

Illustrative structure only — actual shares vary widely by product category and order size. Verify against your own quotes.
Line itemWhat it coversTypical share of unit price
Raw materials (BOM)Fabric, resin, metal, board — the physical inputs25–45%
Components & hardwareZippers, fasteners, electronics, trims, labels10–25%
Processing / laborCutting, sewing, molding, assembly, finishing12–25%
PackagingPrimary pack, polybag, master carton, inserts3–8%
Tooling amortizationMoulds, dies, screens, patterns — spread over units0–8%
QC & testingIn-process inspection, final inspection, lab tests1–4%
Overhead allocationFactory rent, utilities, equipment depreciation, admin5–12%
Factory marginTheir profit — the part you're negotiating over8–18%

Notice the last line: the part you haggle over is usually the smallest slice. That is the whole argument for cost engineering over price squeezing — see section 6.

2. Worked teardown: one unit, line by line

Here is the same $12.00 FOB unit, opened up. The numbers are illustrative — they exist to show the shape of a quote, not to be copied into your budget.

Illustrative example for teaching the structure — not a price benchmark for any category.
LinePer unitShare
Raw materials (BOM)$4.2035%
Components & hardware$1.8015%
Processing / labor$2.4020%
Packaging$0.726%
Tooling amortized over the run$0.363%
QC & testing$0.242%
Factory overhead allocation$0.968%
Factory margin$1.3211%
Quoted unit price (FOB)$12.00100%

Now read it as an operator. Materials plus components are $6.00 — half the price. That is where a spec change moves real money. The factory's margin is $1.32; even a heroic negotiation that removes a third of it saves you 44 cents, while a material substitution approved by engineering could save $1.20 or more. Same effort, three times the result, no damaged relationship.

3. The costs nobody quotes

These are the lines that wreck first budgets, because they sit outside the unit price entirely. Ask about every one of them before you commit:

Vetting the factory is what stops these from becoming disputes later. Use the factory audit checklist →

4. From FOB to landed cost

Landed cost is the only number that matches your bank account. Build it as separate lines — a single "+30%" multiplier is the most common budgeting mistake new importers make, because freight is driven by volume and chargeable weight while duty is driven by your HS code and destination. Two products with the same FOB price can land at very different costs.

Illustrative — freight depends on density and mode; duty depends on your HS code and market.
ComponentIllustrative per unit
FOB unit price$12.00
Ocean freight allocation$0.85
Marine insurance$0.10
Import duty (illustrative 12% of FOB)$1.44
Customs brokerage & port charges$0.30
Inland delivery to your warehouse$0.55
Estimated landed cost per unit$15.24

$12.00 quoted → roughly $15.24 landed, or about +27%. Every point of that is negotiable in a different place, which is exactly why you want the lines separated.

5. How to compare two quotes properly

Two quotes for "the same product" are rarely for the same product. Normalize before you compare:

  1. Confirm the Incoterm is identical on both.
  2. Request a line-by-line breakdown from each supplier, using the same categories.
  3. Match the material grade and component brands — not just the item name.
  4. Match the packaging standard (individual boxing, master carton spec).
  5. Confirm whether tooling, samples, and testing are included or extra.
  6. Compare MOQ, lead time, and defect allowance — not only price.
  7. Ask each for pricing at 1×, 3×, and 5× volume to expose their real cost curve.

6. Where the real savings are

Ranked by how much they typically move, and how little damage they do to the relationship:

One warning: do not squeeze the margin line past the point where the factory can make money. Below that threshold, the cost comes back to you as silent material substitution or skipped inspection — and you find out after the goods ship.

Volume tiers and minimums are the flip side of this same conversation. Read the MOQ negotiation guide →

7. Cost breakdown request template

Send this the moment a quote arrives. Suppliers who answer it well are usually the ones worth working with; suppliers who refuse the breakdown are telling you something.

Subject: Cost breakdown request — [Product], [Order quantity] Hi [Name], Thank you for the quote of [price] per unit on [Incoterm, e.g. FOB Shenzhen]. Before we proceed, could you send a line-by-line cost breakdown using these categories: 1. Raw materials (by material, with grade/spec) 2. Components and hardware (with brand or spec where applicable) 3. Processing / labor 4. Packaging (primary pack and master carton) 5. Tooling or mould charges (one-time) and how they amortize 6. QC and testing 7. Factory overhead and margin Also please confirm separately: - Which Incoterm this price is quoted on - Sample cost, express shipping, and how many revision rounds are included - Whether compliance testing for [market: EU / US / other] is included - MOQ, lead time, and your standard defect allowance - Unit pricing at 1x, 3x, and 5x this quantity - Who owns the tooling, and whether it can be transferred Happy to jump on a short call if that's faster. Best regards, [Your name]

Start from the full picture if you're early in the process — read the complete sourcing playbook →

FAQ

What does a factory quote usually include?

A standard Chinese factory quote covers the physical product: raw materials and components (BOM), processing and labor, packaging, and the factory's own overhead and margin. It usually excludes tooling, samples, compliance testing, inland transport to port, freight, insurance, duties, and customs brokerage — which is why the quote is never the final cost.

What is the difference between EXW, FOB, and landed cost?

EXW is the factory gate price — you arrange everything from pickup onward. FOB adds inland transport and export clearance to the Chinese port, with the buyer paying ocean or air freight. Landed cost adds freight, insurance, duties and tariffs, customs brokerage, and final inland delivery to your door. Landed cost is the only number that reflects what actually leaves your bank account.

How much should I add to an FOB price to estimate landed cost?

It depends heavily on product density, shipment size, mode of transport, and the duty rate for your HS code in your destination market. Rather than applying a fixed percentage, build the landed cost line by line — freight based on chargeable weight or volume, duty based on your HS code, plus brokerage and inland delivery. A single flat multiplier is the most common budgeting mistake first-time importers make.

Why do two factories quote very different prices for the same product?

Usually because the quotes are not for the same thing. Differences hide in material grade, component brand, tolerance, finishing, packaging standard, defect allowance, and whether tooling or testing is included. Always request a line-by-line breakdown and compare specifications side by side before comparing prices.

Is squeezing the unit price the best way to reduce cost?

Rarely. Unit price is the last and smallest lever, and pushing it below a factory's viable margin invites silent material substitution or skipped QC steps. The larger levers are specification and BOM re-engineering, packaging optimization, shipment consolidation, payment and FX terms, and volume tiering.